Cork Flooring in Kitchen - Installation instruction !

A floating cork flooring in kitchen is INSTALLED LAST!

It must be noted that enough people have asked enough questions to warrant a sub-section on installing a floating floor in a kitchen.

Please note: A cork flooring kitchen installation requires two coats of water based polyurethane!

When sealing the floor with polyurethane, you are not “sealing” the cork, you are sealing the seams. This is to protect the HDF or High Density Fibreboard from water damage. You are also protecting your subfloor from water damage.

kitchen ideas, kitchen designs, kitchen remodeling, kitchen remodel, modern kitchen, kitchen tile,

*For a basic, step by step, floating floor installation please visit our “Installation Guide for Floating Flooring”.


Materials required to complete this project:
space1. Cork Floating Flooring (acclimatized x 48-72hours)
space2. Loba Supra Satin Polyurethane or Polywhey water based polyurethane
space3. Kitchen/bath caulking (found at any hardware store worth its salt)
space4. Tape measurer and pencil
space5. Saw
space6. Hammer or mallet
space7. Tapping block (can be made out of samples of your cork floor)
space8. 1/2 inch spacers or shimmies (can be made out of samples or off cuts)
space9. Fine napped paint roller (an extension handle can save your back a lot of grief)
space10. Medium sized container for mixing the 2 part Loba Supra Satin Polyurethane
space11. Paint tray to hold the Polywhey polyurethane mixture


Allow the caulking time to dry.


Polyurethane Application:

Mix your 2 part Loba polyurethane in a water tight container (ALWAYS follow the directions on the original container). Make sure you mix only the amount needed to seal your floor in 1 (one) coat. Leave the rest of the unmixed OV

urethane in the original containers and seal the containers immediately.

Do NOT premix the Loba polyurethane! Once mixed it has a small window of liquidity before it sets! Do NOT try to recap the container after four hours! A build-up of pressure could cause the container to burst!

Time Count Violation: Once the 2 part epoxy has been mixed you only have 3 hours of working time before the mixture hardens to become plastic. Once mixed, DO NOT RECAP or put a lid on the mixture after the four hour mark! Intense build-up of pressure may result in a very unpleasant event (like the container exploding)!

Measure out the appropriate amount of varnish and hardener into a container (many people use old yogurt containers) and shake vigorously. The varnish will change to a milky white substance. This is the colour you are looking for.

Allow polyurethane 4-6 hours to dry. The finish may be dry but it has not had time to cure. Any form of footwear that has a tread my leave imprints in the still-soft coat of polyurethane. After 24 hours the floor is available for light use (stocking feet only).

After 4-6 hours has passed the second coat can then be applied. The same rule applies when waiting for the second coat to dry. Once it has dried a curing time of up to 5 days should be observed. That means stocking feet and light traffic only. Do not place mats or rugs over the area until after the floor has been fully cured.

My personal recommendation to home owners who are remodeling their kitchen is this:

Apply the first coat of polyurethane in the evening. Once you have finished with your kitchen for the evening, apply your first coat. Put a chair with a little note on it to remind those “midnight snackers” to stay off the floor. The over-night period should be more than 8 hours in duration before anyone is allowed to use the kitchen the next day. Test your floor you’re your floor before walking on it! Overall temperature and humidity levels can cause a slower or faster dry time than what it says on the label.

The next day, go ahead and use the kitchen floor lightly and only with socks on your feet! Recoat your floor the same way the next evening following the same routine. By applying the varnish at night you will effectively give yourself almost 24 hours of curing time before the next coat is applied. This way you have the use of your kitchen while at the same time letting the floor cure.

You are all done! Congratulations, you have just installed a floating cork floor in an area that 10 years ago experts would have told you, “Never, ever in a kitchen!”!

Keyword water damage water based polyurethane, floor installation guide in tiles reviews in durability pros and cons plank for in installation, Cork Flooring in Kitchen natural floating prices cost cheap best discount in basement laminate cost of glue down linoleum floors board hard engineered rubber vinyl options linoleum engineered vinyl plank basement ideas cabinets carpet bathroom marmoleum ceramic tile parquet porcelain countertops discount design ideas engineered basement, islands slate remodeling planks remodel island floor options bamboo layouts cabinet doors liquidators small design, Cork Flooring in Kitchen designs modern remodel ideas ikea kıtchen design wall renovation underlayment ideas oak design software, ceramic makeovers island ideas designer cabinet hard cabinet ideas cheap laminate wicanders what is how to install backsplash ideas marmoleum covering prices modern kitchens wood benefits of pictures water damage, Cork Flooring in Kitchen restoration cabinets to go buy vinyl for commercial decorating ideas by design types of backsplash, review outdoor us cabinet refacing remodels galley design a companies small ideas plans plans sale ikea remodel, cost pros and cons in room planner vinyl vinyl beautiful custom pros and cons small remodel décor cabinet refacing, Cork Flooring in Kitchen for engineered island design planner ideas for small